Friday, November 18, 2011

It's a Wonderful Wall

The kids and I snuck down to watch Mike and his crew start working on the walls right after breakfast this morning.

While down there, Mike went over a couple minor changes (I hope) to make it easier to build - such as straightening a wall instead of including a slight jag in the wall and moving the opening under the stairs to the side room instead of off the hallway. He also verified we wanted to do a single door centered in the room with windows on either side about a foot from the door on either side (yes, in case you were wondering).

Then we watch Mike and his buddy Darryl (I believe...) mark off the floor for the load bearing walls.


Mike says it usually takes them 5-6 weeks to frame all the way up to the roof - but it might take a little longer with Thanksgiving and Christmas being a part of those weeks.

The crew started placing boards along the top of the walls.

We headed back to let them get some real work done without worrying about kids being underfoot. Kids (eh, hem - NIKKI!) + Powertools = No Good!

After lunch and school, I quickly went down to see the progress - and WOW!

We have WALLS!!

Ok, so they are still framing them up - but they are there!

We are also having blocks laid for part of the wall so we won't have as much expense when we brick up the house later. Yup - we're going brick - hopefully with some stone accents too.




Then Tom came home early so we grabbed the kids and leisurely walked down to see what they completed today.

Nikki inspecting the HVAC pipes. They are in the chalk-line walls, so we'll have to see if that's intentional or not. If not, who knows what will happen. Here's hoping it's intentional.

My cuties!

Such a good looking bunch. :)

Tom pointed out the marks the hinge in the forms left behind. Never noticed it before. Pretty cool.

View from the back storage room.

View of same storage room and future bedroom.

Silly girl!

Our mostly finished wall.

The center door seems to be off a little from the opening in the cement slab, so we'll talk to Mike on Sunday to see what's happening there. I thought the cement opening was center, but maybe it isn't. I didn't have a tape measure, so we'll see.

View from the retaining wall.

View from above.

Bye house - see you next week when more wall stuff happens.

Pin It!

Thursday, November 17, 2011

Slab it on thick!

I convinced my hubby to go to work late today because...the cement trucks are coming again today to pour our basement slab! They brought back the pump truck - and man is that thing cool! Plus, there was a chance one of the trucks would get stuck in the mud since yesterday we found out the UPS truck got stuck in the mud at our house and had to get towed out. How could Tom miss a chance like that, right?

So, after breakfast we bundled the kids up and headed down to see it all take place. 

It's a little crazy down there. Not only are we getting our slab poured, but the lumber was also delivered last night, so they are working on creating the headers for the walls today. Tomorrow they plan to start building the walls. CRAZY FUN!


They laid down wire mesh to firm up the cement. 


Our beautiful model Becky.

Then the kids and I took our seats to watch the pouring begin. 

Nikki was a little too excited and decided to pretend to be a mountain goat/jaguar. 

Then they began. The cement truck backed up to the pump truck and dumped cement into the loader. 


First the cement shot out. Next they started spreading it out and smoothing the edges. Finally they pulled out a larger version of their smoother and smoothed out a HUGE section at a time. That thing has a motor that pulses it just enough to knock the large rock chunks down and bring up the smoother particles of the cement. It was so cool to watch. 
 

While this was taking place, Mike had his guys building headers and a storage box for nails and other misc. things.  So there was a lot of cutting, nailing, measuring, and cutting again. 

Unfortunately, it was time for Tom to head off to work, and for the kids and I to head inside to do school & have lunch. So, after gobbling down lunch, Tommy and I ran back out to see what had happened. 

 They were almost finished pouring the last of the cement. 

So we watched them finish it up... 

and smooth it out...

and then they were done.

Isn't our slab beautiful??
View from side of basement.
 Screwing down the boards.
 I don't know why, but I LOVE this shot. 
 
 Our slab from above.

 

Then they brought out the polisher and polished it up all pretty.

I actually don't know what it's called, but it buffs the cement up nice and smooth, making it all pretty.

Tommy's getting better with his smiles at the camera! Yay!

View of the tar on the front of the house - never saw it from this angle, so thought I'd show it while it was still  free of dirt.
French drain in the Main Garage.
Now that the cement had been poured, it was time to cleanup the pump truck. This time we stuck around to watch the cleanup process. They dumped the remaining cement from the pump truck into our garage - trying to be useful with where they put the cement. 

 Then the driver got out a large sponge. The sponge is soaking wet and they just squeeze it into the end of the pump pipe and then reverse the suction and VOILA - clean pump truck. 

Well, as clean as that thing can get. It is cement after all. But the inside is cleaner - right?

We waved goodbye to the pump truck, and then...every man-who-owns-a-truck's dream came true. The pumper truck got stuck in the mud. 

So everyone ran to their truck to grab chains and ropes and whatever else is manly and needed to pull a truck out of the mud. 

Then they hooked the pumper up and pulled...and pulled...and pulled...and NOTHING. 

So they tried again, with wheels smoking...

and tires spinning... 

And finally...

Success!!!

Bye Bye Pump Truck! We'll miss you!

Well, maybe not so much, seeing the mess left behind. 

At least that's fixable when Clint comes again...next week, we hope. :)
Pin It!

Friday, November 11, 2011

My TODO Lists

 Between homeschooling my kids, working part time, keeping house, running errands, selling our old house, and building a new house (want me to keep going?), my life feels like it is snowballing out of control. I'm afraid I won't take care of everything I'm supposed to in a timely fashion. I've perused Pinterest quite a bit, and followed some of my favorite blogs, looking for the perfect daily or weekly planner for me, but sadly could not find the perfect one. The one I'd want to use every day. The one that would keep me from dropping all the balls I'm currently juggling. The one that would track house projects, cleaning projects, exercise & food, and people to call. Nothing too picky, right? 

So, I decided to make my own. I wanted something simple that would let me check off a simple cleaning list that would help me easily keep the house clean and keep me motivated to get it done because it could be done quickly. I also need something to write down the important things I have to do today and people I need to call. I also wanted to start meal planning, so there also needed to be a place for that.  With all my needs/wants, I decided to make two lists. One to give me an overview of what I should do today, tomorrow, and sometime later in the week, and one that would give me the chores I have to complete today to keep my house nice.

Here's what I came up with. 

I'm still playing around with it, but I think my weekly and daily cleaning lists are where I want them to be for now. I'm thinking about maybe making a monthly one too, but will have to see how my weekly and daily lists keep me movtivated and on track. :) I'm also playing around with my monthly food & exercise log. It works, but isn't as pretty as I want it to be, plus I found some other cool features I wanted to add to it. Guess it will have to wait for some more free time! 
Pin It!